93 %
Salle de bain et sanitaires
Current stage : Finitions et nettoyage 6 stages completed out of 7
Site stages
-
Projet confirmé
Completed3 October 2026
Edit
-
Démolition de l'ancienne salle de bain
Completed11 October 2026
1 photo(s)
Edit
-
Plomberie et évacuations
Completed18 October 2026
1 photo(s)
Edit
-
Étanchéité et chape
Completed25 October 2026
Edit
-
Faïence et carrelage
Completed2 November 2026
1 photo(s)
Edit
-
Pose des sanitaires
Completed9 November 2026
1 photo(s)
Edit
-
Finitions et nettoyage
In progress11 November 2026